UPDATE 6/5/2026
Below you will find the latest updates for the Remington Avenue Streetscape Project:
- Construction of a retention pond near the Thomas County Emergency Services building continues. This project is not a part of the Remington Avenue Streetscape Project but will greatly improve stormwater movement throughout the corridor.
- Extensive water services and line work continues along Remington Avenue beyond the Thomas County Emergency Services building.
- Phase II sidewalk construction continues along Remington Avenue toward Ben Grace Drive. Work may slow temporarily as the water extension project progresses to the water line tie-in at East Pinetree Boulevard.
- Traffic signal poles have been installed at the intersection of Remington Avenue and Covington Avenue. Connection work continues.
- Eastbound Remington Avenue at the roundabout remains closed to minimize traffic due to continued construction work.
- Travelers in the area are reminded of the dangers of driving around barricades and through active construction areas. Drivers are asked to use established detours to bypass the construction area.
We ask citizens to be mindful of their speed while traveling through the corridor and along posted detours.